0.1 / 0.05 / 0.02 HzWithstand testing
VLF hipot
Assess dielectric withstand in capacitive loads, particularly cables.
How and when to use
WHEN TO USE
During cable commissioning or maintenance under the applicable procedure. For large motors and generators, only when the method is approved for their insulation.
HOW IT WORKS
Applies high voltage at very low frequency, controlling the ramp and measuring voltage, current and waveform. Configuration depends on asset capacitance.
HOW TO INTERPRET
Evaluates whether insulation withstands the specified test. It does not measure insulation resistance or locate a fault on its own.
FIELD CONFIGURATION
Select voltage and load capacity; the datasheet lists up to 80 kV peak depending on configuration.